1 00:00:19,429 --> 00:00:16,300 [Music] 2 00:00:22,189 --> 00:00:19,439 Saturn one 1b quarterly film report 3 00:00:33,049 --> 00:00:22,199 number 24 covers progress during the 4 00:00:34,819 --> 00:00:33,059 period April May June 1965 highlighting 5 00:00:37,850 --> 00:00:34,829 this quarter was the successful launch 6 00:00:40,520 --> 00:00:37,860 in flight of the night Saturn one si8 7 00:00:42,380 --> 00:00:40,530 and the equally successful orbiting of 8 00:00:45,500 --> 00:00:42,390 the second meteoroid technology 9 00:00:46,130 --> 00:00:45,510 satellite Pegasus B at the beginning of 10 00:00:48,139 --> 00:00:46,140 the quarter 11 00:00:52,430 --> 00:00:48,149 the launch vehicle had been erected at 12 00:00:54,560 --> 00:00:52,440 the Cape and was being tested on April 13 00:00:57,049 --> 00:00:54,570 10th following preparations for shipment 14 00:01:00,080 --> 00:00:57,059 the service module and its adapter for 15 00:01:03,380 --> 00:01:00,090 Apollo boilerplate number 26 was flown 16 00:01:05,570 --> 00:01:03,390 from Marshall to the Cape meanwhile 17 00:01:07,630 --> 00:01:05,580 final checkout of Pegasus B was 18 00:01:10,190 --> 00:01:07,640 completed at Hagerstown Maryland 19 00:01:11,570 --> 00:01:10,200 following checkout the satellite was 20 00:01:14,810 --> 00:01:11,580 shipped to General Electric for 21 00:01:15,230 --> 00:01:14,820 vibration tests April 13th two days 22 00:01:19,429 --> 00:01:15,240 later 23 00:01:22,039 --> 00:01:19,439 Pegasus B was shipped to the Cape in 24 00:01:24,980 --> 00:01:22,049 mid-april Pegasus B underwent system 25 00:01:26,690 --> 00:01:24,990 checks in hangar D following testing the 26 00:01:28,999 --> 00:01:26,700 satellite was mated to boiler plate 27 00:01:33,140 --> 00:01:29,009 number 26 is service module and it's 28 00:01:35,359 --> 00:01:33,150 adapter April 27th on April 28 the 29 00:01:38,870 --> 00:01:35,369 spacecraft was moved to the launch pad 30 00:01:40,569 --> 00:01:38,880 and directed atop si8 direction of the 31 00:01:44,389 --> 00:01:40,579 command module followed immediately 32 00:01:46,609 --> 00:01:44,399 flight objectives of si8 were to provide 33 00:01:49,429 --> 00:01:46,619 and evaluate meteoroid data in near 34 00:01:51,560 --> 00:01:49,439 Earth orbit demonstrate launch vehicle 35 00:01:54,620 --> 00:01:51,570 iterative guidance mode and evaluate 36 00:01:57,910 --> 00:01:54,630 system accuracy and test a closed-loop 37 00:02:00,740 --> 00:01:57,920 guidance system for the fourth time 38 00:02:02,959 --> 00:02:00,750 pre-launch check out of si8 progressed 39 00:02:06,440 --> 00:02:02,969 satisfactorily countdown demonstration 40 00:02:13,770 --> 00:02:06,450 test incompletes May 21st countdown 41 00:02:32,170 --> 00:02:17,260 vehicle liftoff occurred on May 25th at 42 00:02:34,330 --> 00:02:32,180 2:35 a.m. Eastern Standard Time si8 the 43 00:02:36,220 --> 00:02:34,340 first vehicle to use a chrysler built 44 00:02:38,950 --> 00:02:36,230 booster was the night straight 45 00:02:51,480 --> 00:02:38,960 successful Saturn the first stage burned 46 00:02:57,070 --> 00:02:54,970 the second stage burned about 474 47 00:02:59,500 --> 00:02:57,080 seconds obtaining programs cutoff 48 00:03:04,000 --> 00:02:59,510 velocity stage performance was 49 00:03:06,310 --> 00:03:04,010 satisfactory the Apollo command and 50 00:03:08,320 --> 00:03:06,320 service module jettisoned mechanically 51 00:03:11,260 --> 00:03:08,330 and the Pegasus wings successfully 52 00:03:13,930 --> 00:03:11,270 deployed Pegasus bees roll rate was six 53 00:03:16,210 --> 00:03:13,940 point six degrees per second as compared 54 00:03:18,790 --> 00:03:16,220 to Pegasus age roll rate of nine point 55 00:03:21,010 --> 00:03:18,800 eight degrees Pegasus B like its 56 00:03:23,170 --> 00:03:21,020 predecessor is successfully obtaining 57 00:03:25,570 --> 00:03:23,180 information concerning quantity and 58 00:03:41,860 --> 00:03:25,580 penetrating ability of meteoroids in the 59 00:03:44,260 --> 00:03:41,870 near-earth orbit the remaining Pegasus 60 00:03:46,090 --> 00:03:44,270 satellite will be launched by SI ten 61 00:03:50,890 --> 00:03:46,100 which throughout the quarter has been 62 00:03:53,170 --> 00:03:50,900 undergoing preparations for launch at 63 00:03:55,960 --> 00:03:53,180 Marshalls Michou operations preparations 64 00:04:00,760 --> 00:03:55,970 for shipment of s1 10 continued during 65 00:04:03,100 --> 00:04:00,770 April and May on May 26th the booster 66 00:04:06,930 --> 00:04:03,110 departed via barge for Cape Kennedy and 67 00:04:16,030 --> 00:04:09,910 two days later it was erected on the pad 68 00:04:21,590 --> 00:04:19,220 s410 was removed from storage at Sacto 69 00:04:26,930 --> 00:04:21,600 then loaded aboard the guppy and flown 70 00:04:29,210 --> 00:04:26,940 to KSC arriving may 8 inch a cow and 71 00:04:34,280 --> 00:04:29,220 necessary painting the stage was erected 72 00:04:36,620 --> 00:04:34,290 atop s110 the evening of June 8 check 73 00:04:39,020 --> 00:04:36,630 out of SIU 10 was completed in early 74 00:04:41,450 --> 00:04:39,030 April preparations for shipment of the 75 00:04:43,190 --> 00:04:41,460 instrument unit 4 completed April 16th 76 00:04:47,480 --> 00:04:43,200 when it was temporarily placed in 77 00:04:50,720 --> 00:04:47,490 storage on June 1st 78 00:04:53,000 --> 00:04:50,730 SIU 10 was delivered to the Cape on June 79 00:04:55,490 --> 00:04:53,010 night following checkout alignment and 80 00:04:58,370 --> 00:04:55,500 painting the unit was erected atop the 81 00:05:03,050 --> 00:04:58,380 stages pre-launch checkout of stages and 82 00:05:04,610 --> 00:05:03,060 components is underway while preferring 83 00:05:07,130 --> 00:05:04,620 checkout of the launch vehicle was 84 00:05:10,040 --> 00:05:07,140 underway modifications were completed on 85 00:05:11,840 --> 00:05:10,050 Apollo boiler plate number 9 the service 86 00:05:17,270 --> 00:05:11,850 module and adapter were shipped from 87 00:05:19,130 --> 00:05:17,280 Marshall to the Cape June 20th the 88 00:05:22,340 --> 00:05:19,140 command module and launch escape system 89 00:05:24,680 --> 00:05:22,350 were shipped on June 29th following 90 00:05:26,510 --> 00:05:24,690 mating with Pegasus boiler plate number 91 00:05:31,280 --> 00:05:26,520 nine will be erected atop the launch 92 00:05:33,560 --> 00:05:31,290 vehicle early next quarter Pegasus e 93 00:05:35,990 --> 00:05:33,570 electronic canister and thermal vacuum 94 00:05:39,380 --> 00:05:36,000 testing was completed at Bladensburg 95 00:05:41,300 --> 00:05:39,390 Maryland May 26 the satellite was then 96 00:05:43,400 --> 00:05:41,310 shipped to Fairchild Hiller's Hagerstown 97 00:05:46,420 --> 00:05:43,410 facility for final assembly and 98 00:05:50,270 --> 00:05:46,430 functional checkout 99 00:05:52,490 --> 00:05:50,280 Pegasus C were shipped to KSC June 22nd 100 00:05:54,409 --> 00:05:52,500 where it will receive pre-launch check 101 00:05:58,610 --> 00:05:54,419 out prior to mating with boiler plate 102 00:06:00,860 --> 00:05:58,620 number nine the launch of Pegasus II and 103 00:06:11,420 --> 00:06:00,870 sa 10 is scheduled for early next 104 00:06:12,890 --> 00:06:11,430 quarter at Marshall Saturn 1b dynamic 105 00:06:15,560 --> 00:06:12,900 testing of the complete vehicle 106 00:06:18,680 --> 00:06:15,570 configuration started last quarter was 107 00:06:22,300 --> 00:06:18,690 successfully completed May 27 no major 108 00:06:24,860 --> 00:06:22,310 problems were encountered during testing 109 00:06:26,180 --> 00:06:24,870 at the present time changeover is 110 00:06:28,010 --> 00:06:26,190 underway to the upper stage 111 00:06:29,390 --> 00:06:28,020 configuration which will allow 112 00:06:31,340 --> 00:06:29,400 simulation of s4 113 00:06:33,499 --> 00:06:31,350 be flight conditions following 114 00:06:38,930 --> 00:06:33,509 completion of change over next quarter 115 00:06:40,550 --> 00:06:38,940 dynamic testing will resume s1 bt has 116 00:06:42,350 --> 00:06:40,560 been shipped to the Michou assembly 117 00:06:44,779 --> 00:06:42,360 facility for storage and such 118 00:06:46,700 --> 00:06:44,789 modifications as necessary for the 119 00:06:51,590 --> 00:06:46,710 Saturn 1b sent our launch vehicle 120 00:06:54,110 --> 00:06:51,600 dynamic test program in April at 121 00:06:56,689 --> 00:06:54,120 Chrysler Michou a failure during the s1 122 00:07:00,409 --> 00:06:56,699 be structural testing revealed a spider 123 00:07:02,659 --> 00:07:00,419 beam marginal design MSFC and Chrysler 124 00:07:05,480 --> 00:07:02,669 investigated the failure resolved the 125 00:07:07,939 --> 00:07:05,490 problem and modified the beam on June 126 00:07:10,850 --> 00:07:07,949 19th the modified spider beam was 127 00:07:25,580 --> 00:07:10,860 successfully tested to the required 140 128 00:07:28,040 --> 00:07:25,590 percent load a major milestone in the 129 00:07:31,159 --> 00:07:28,050 Saturn 1b program was the static firing 130 00:07:33,409 --> 00:07:31,169 at Marshall of the first 1b booster on 131 00:07:35,990 --> 00:07:33,419 April 1st the booster built by Chrysler 132 00:07:39,469 --> 00:07:36,000 was successfully fired for a duration of 133 00:07:41,960 --> 00:07:39,479 35 seconds on April 13th and equally 134 00:07:46,460 --> 00:07:41,970 successful long duration firing was 135 00:07:48,589 --> 00:07:46,470 accomplished the stage was removed from 136 00:07:51,320 --> 00:07:48,599 the static test stand and transported to 137 00:07:54,230 --> 00:07:51,330 Marshalls loading docks on April 20th 138 00:07:57,800 --> 00:07:54,240 the stage departed MSFC and arrived at 139 00:08:00,230 --> 00:07:57,810 me Shu four days later following 140 00:08:03,320 --> 00:08:00,240 completion a post static modification 141 00:08:06,260 --> 00:08:03,330 post static checkout began June 11 the 142 00:08:08,719 --> 00:08:06,270 checkout will be completed in July the 143 00:08:11,060 --> 00:08:08,729 stage is scheduled to arrive at KSC in 144 00:08:13,580 --> 00:08:11,070 mid-august for use in the checkout of 145 00:08:18,700 --> 00:08:13,590 launch complex 34 prior to beginning 146 00:08:22,159 --> 00:08:18,710 pre-flight check also at Chrysler me Shu 147 00:08:25,550 --> 00:08:22,169 s1 b202 pre static checkout was 148 00:08:28,010 --> 00:08:25,560 completed April 22nd on May 21st 149 00:08:29,839 --> 00:08:28,020 installation of retrofitted engines was 150 00:08:33,490 --> 00:08:29,849 completed along with the necessary 151 00:08:35,930 --> 00:08:33,500 electrical tests and engine alignment 152 00:08:38,870 --> 00:08:35,940 the stage was then prepared for shipment 153 00:08:41,500 --> 00:08:38,880 to Marshall departing Mishu June 12th 154 00:08:44,889 --> 00:08:41,510 arriving at MSFC June 19 155 00:08:48,940 --> 00:08:44,899 s1b 202 is scheduled to be static fired 156 00:08:52,090 --> 00:08:48,950 early next quarter at Michou Chrysler 157 00:08:55,120 --> 00:08:52,100 completed Assembly of s 1 B 2 o 3 June 158 00:08:56,980 --> 00:08:55,130 16th following installation pre static 159 00:09:01,720 --> 00:08:56,990 checkout of the booster started June 160 00:09:05,590 --> 00:09:01,730 17th and continued throughout June on 161 00:09:08,710 --> 00:09:05,600 April 5th s1 b204 tank clustering began 162 00:09:10,720 --> 00:09:08,720 with completion in early June assembly 163 00:09:14,949 --> 00:09:10,730 operations on the booster will continue 164 00:09:17,410 --> 00:09:14,959 into August fabrication of s 1 B 2 O 5 165 00:09:20,290 --> 00:09:17,420 major structural components continued 166 00:09:22,329 --> 00:09:20,300 through the quarter on May 12th Assembly 167 00:09:24,910 --> 00:09:22,339 of the second stage adapter was begun 168 00:09:28,870 --> 00:09:24,920 with tank clustering scheduled for July 169 00:09:31,720 --> 00:09:28,880 12th fabrication operations for s1 B 206 170 00:09:35,470 --> 00:09:31,730 are also underway the lower thrust ring 171 00:09:37,720 --> 00:09:35,480 was completed on May 14th on June 28 the 172 00:09:39,579 --> 00:09:37,730 barrel assembly was completed stage 173 00:09:46,480 --> 00:09:39,589 fabrication will continue through next 174 00:09:49,750 --> 00:09:46,490 quarter at Rocketdyne Santa Susana 175 00:09:52,240 --> 00:09:49,760 facility 200k h1 engine qualification 176 00:09:55,180 --> 00:09:52,250 testing begun last quarter was completed 177 00:09:57,400 --> 00:09:55,190 April 30th the test program included 178 00:09:59,470 --> 00:09:57,410 functional and reliability tests of the 179 00:10:03,579 --> 00:09:59,480 locks valve turbo pump and thrust 180 00:10:14,650 --> 00:10:03,589 chamber 8 200k h1 engines will power the 181 00:10:17,140 --> 00:10:14,660 s-1 B stains another Saturn 1b major 182 00:10:19,870 --> 00:10:17,150 milestone was reached at sacto when the 183 00:10:22,630 --> 00:10:19,880 final 1b s4v battleship tests were 184 00:10:24,910 --> 00:10:22,640 performed during May on May 4th a 185 00:10:27,730 --> 00:10:24,920 successful full gimbal full duration 186 00:10:29,980 --> 00:10:27,740 firing was performed on May 14th 187 00:10:32,470 --> 00:10:29,990 successful environmental temperature 188 00:10:34,750 --> 00:10:32,480 conditioning tests were conducted these 189 00:10:37,480 --> 00:10:34,760 concluded the Saturn 1b battleship 190 00:10:42,220 --> 00:10:37,490 program conversion of the stage 2 Saturn 191 00:10:45,220 --> 00:10:42,230 5 configuration began immediately also 192 00:10:46,840 --> 00:10:45,230 at Sacramento the s4b facilities 193 00:10:49,329 --> 00:10:46,850 checkout stage underwent successful 194 00:10:51,690 --> 00:10:49,339 propellant loading tests at Douglass's 195 00:10:54,940 --> 00:10:51,700 beta test and number three this quarter 196 00:10:57,520 --> 00:10:54,950 qualifying both the stage and test and 197 00:10:59,710 --> 00:10:57,530 on May first automatic loading tests 198 00:11:01,630 --> 00:10:59,720 were successfully completed following 199 00:11:04,540 --> 00:11:01,640 testing the stage was removed from the 200 00:11:06,190 --> 00:11:04,550 stand and moved to an inspection site no 201 00:11:08,230 --> 00:11:06,200 discrepancies were revealed during 202 00:11:11,860 --> 00:11:08,240 post-test inspections of the propellant 203 00:11:14,620 --> 00:11:11,870 tanks lh2 tank insulation and dye checks 204 00:11:16,390 --> 00:11:14,630 of all exposed Wells the stage was 205 00:11:18,580 --> 00:11:16,400 subsequently prepared for shipment at 206 00:11:21,250 --> 00:11:18,590 Sacto and departed by a water 207 00:11:24,070 --> 00:11:21,260 transportation for KSC June 10th 208 00:11:26,260 --> 00:11:24,080 arriving June 30th the stage will be 209 00:11:30,910 --> 00:11:26,270 used in the checkout of launch complex 210 00:11:33,450 --> 00:11:30,920 34 construction of the vertical checkout 211 00:11:36,070 --> 00:11:33,460 laboratory at Sacto is well underway 212 00:11:38,140 --> 00:11:36,080 erection of structural steel is complete 213 00:11:40,030 --> 00:11:38,150 and installation of handling and test 214 00:11:42,730 --> 00:11:40,040 equipment is underway following 215 00:11:45,250 --> 00:11:42,740 acceptance the facility will be used for 216 00:11:49,240 --> 00:11:45,260 post static check out of s4v stages 217 00:11:51,220 --> 00:11:49,250 after acceptance firing a tear 218 00:11:53,650 --> 00:11:51,230 researchers test facility in Phoenix 219 00:11:56,260 --> 00:11:53,660 Arizona qualification testing of the 220 00:11:59,140 --> 00:11:56,270 fuel feed duct for s4b stages was 221 00:12:01,540 --> 00:11:59,150 conducted this quarter at Douglass's 222 00:12:05,920 --> 00:12:01,550 Huntington Beach facility the first s4b 223 00:12:07,810 --> 00:12:05,930 flight stage s4v 201 underwent lh2 tank 224 00:12:10,780 --> 00:12:07,820 modifications parts shortage 225 00:12:12,820 --> 00:12:10,790 installation painting and weighing the 226 00:12:16,360 --> 00:12:12,830 stage was then shipped to sacto April 227 00:12:18,670 --> 00:12:16,370 30th arriving May 6th the next day it 228 00:12:20,860 --> 00:12:18,680 was installed in beta test stand number 229 00:12:23,830 --> 00:12:20,870 3 we're out of position installations 230 00:12:26,350 --> 00:12:23,840 and modifications were begun pre static 231 00:12:29,200 --> 00:12:26,360 checkout began May 29th and continued 232 00:12:31,210 --> 00:12:29,210 through June a major milestone will be 233 00:12:33,160 --> 00:12:31,220 reached early next quarter with the 234 00:12:39,640 --> 00:12:33,170 acceptance firing of the first flight 235 00:12:42,280 --> 00:12:39,650 s4b stage major assembly on s4b 202 was 236 00:12:43,930 --> 00:12:42,290 completed April 30th checkout started 237 00:12:46,240 --> 00:12:43,940 the same day and continued through the 238 00:12:52,060 --> 00:12:46,250 quarter in parallel with installation of 239 00:12:54,940 --> 00:12:52,070 late parts s4b 203 clip bonding is now 240 00:12:56,590 --> 00:12:54,950 complete installations in the LH 2 tank 241 00:12:58,600 --> 00:12:56,600 and component installation in the 242 00:13:03,220 --> 00:12:58,610 forward and aft skirts and thrust 243 00:13:07,120 --> 00:13:03,230 structure continued installation of the 244 00:13:08,010 --> 00:13:07,130 LH 2 tanks for s4b 204 was completed in 245 00:13:10,199 --> 00:13:08,020 May 246 00:13:15,269 --> 00:13:10,209 installation of helium spheres in the 247 00:13:18,180 --> 00:13:15,279 lh2 tank was completed in late May in 248 00:13:20,310 --> 00:13:18,190 early May at santa monica s4b 205 249 00:13:23,220 --> 00:13:20,320 fabrication and assembly of the LOX tank 250 00:13:25,260 --> 00:13:23,230 was completed the LOX tank and lh2 251 00:13:28,470 --> 00:13:25,270 segments were then shipped to Huntington 252 00:13:31,980 --> 00:13:28,480 Beach joining of the lh2 and lox tanks 253 00:13:34,400 --> 00:13:31,990 occurred in mid-may joining of the 254 00:13:37,530 --> 00:13:34,410 forward dome was completed in early June 255 00:13:43,230 --> 00:13:37,540 lh2 insulation is scheduled for next 256 00:13:46,650 --> 00:13:43,240 quarter assembly of s4b 206 aft common 257 00:13:48,960 --> 00:13:46,660 bulkheads started May 4th work continued 258 00:13:55,740 --> 00:13:48,970 on the joining of aft and forward common 259 00:13:58,470 --> 00:13:55,750 bulkheads development and manufacturing 260 00:14:00,780 --> 00:13:58,480 of the s4 B's j2 engine continued 261 00:14:03,000 --> 00:14:00,790 throughout the quarter at status suzana 262 00:14:06,120 --> 00:14:03,010 modifications to rocky tines vertical 263 00:14:08,910 --> 00:14:06,130 stand 3a for j2 engine static tests 264 00:14:11,490 --> 00:14:08,920 started last quarter were completed in 265 00:14:15,540 --> 00:14:11,500 early June initial static firing 266 00:14:17,190 --> 00:14:15,550 occurred in mid April in order to 267 00:14:19,620 --> 00:14:17,200 improve manufacturing workload 268 00:14:22,440 --> 00:14:19,630 distribution Rocketdyne transferred the 269 00:14:24,870 --> 00:14:22,450 j2 liquid oxygen turbo pump fabrication 270 00:14:32,460 --> 00:14:24,880 from Canoga Park California to its 271 00:14:34,230 --> 00:14:32,470 Neosho Missouri plant as part of the 272 00:14:36,960 --> 00:14:34,240 flight rating test program which was 273 00:14:39,090 --> 00:14:36,970 successfully completed on June 30th six 274 00:14:41,010 --> 00:14:39,100 satisfactory malfunction tests were 275 00:14:43,560 --> 00:14:41,020 performed at Santa Susana this quarter 276 00:14:45,690 --> 00:14:43,570 during these tests malfunctions are 277 00:14:47,819 --> 00:14:45,700 deliberately phased into an engine to 278 00:14:49,800 --> 00:14:47,829 determine effect on performance and to 279 00:14:54,000 --> 00:14:49,810 see if a safe shutdown can be 280 00:14:56,400 --> 00:14:54,010 accomplished the other flight rating 281 00:14:58,889 --> 00:14:56,410 tests including altitude testing series 282 00:15:01,440 --> 00:14:58,899 safety limit series and malfunction 283 00:15:07,440 --> 00:15:01,450 series were successfully conducted with 284 00:15:09,900 --> 00:15:07,450 engines 2002 and 2003 at Marshall the 285 00:15:12,449 --> 00:15:09,910 first j2 engine delivered by Rocketdyne 286 00:15:15,120 --> 00:15:12,459 was installed in the static test and in 287 00:15:18,510 --> 00:15:15,130 April it is being used to familiarize 288 00:15:20,400 --> 00:15:18,520 MSFC personnel with the engine a second 289 00:15:21,870 --> 00:15:20,410 engine delivered to Marshall in June 290 00:15:26,490 --> 00:15:21,880 will be used to 291 00:15:28,410 --> 00:15:26,500 activate the stand at Wiley laboratories 292 00:15:30,660 --> 00:15:28,420 Huntsville instrument unit vibration 293 00:15:33,150 --> 00:15:30,670 testing started last quarter continued 294 00:15:34,770 --> 00:15:33,160 through April and May tests revealed 295 00:15:36,650 --> 00:15:34,780 deficiencies in the mounting of 296 00:15:39,630 --> 00:15:36,660 components to the IU structure 297 00:15:41,220 --> 00:15:39,640 consequently it was decided to bolt the 298 00:15:43,950 --> 00:15:41,230 mounting pads to the structure in 299 00:15:45,720 --> 00:15:43,960 addition to bonding additional vibration 300 00:15:49,860 --> 00:15:45,730 tests are underway to qualify the 301 00:15:51,630 --> 00:15:49,870 mechanically fastened mounting pads at 302 00:15:53,460 --> 00:15:51,640 Marshall assembly was completed in 303 00:15:55,620 --> 00:15:53,470 mid-june on the facilities check out 304 00:15:59,700 --> 00:15:55,630 instrument unit the unit was shipped 305 00:16:02,430 --> 00:15:59,710 from MSFC to Michou with s1 BD June 19th 306 00:16:04,530 --> 00:16:02,440 arriving June 23rd it will be 307 00:16:07,560 --> 00:16:04,540 temporarily stored then shipped to the 308 00:16:12,210 --> 00:16:07,570 Cape with s 1 B 201 for a launch complex 309 00:16:14,610 --> 00:16:12,220 34 check out instrument unit structural 310 00:16:16,740 --> 00:16:14,620 testing began May 27th at Marshall 311 00:16:19,440 --> 00:16:16,750 testing revealed a necessity for minor 312 00:16:21,750 --> 00:16:19,450 changes in the IU access door which have 313 00:16:23,340 --> 00:16:21,760 been made to series of tests have been 314 00:16:25,290 --> 00:16:23,350 completed with the third and final 315 00:16:30,210 --> 00:16:25,300 series to be conducted early next 316 00:16:32,070 --> 00:16:30,220 quarter assembly of structural segments 317 00:16:34,470 --> 00:16:32,080 for the second I use structural test 318 00:16:37,020 --> 00:16:34,480 unit began June 8 with completion 319 00:16:38,670 --> 00:16:37,030 scheduled in late July structural 320 00:16:41,100 --> 00:16:38,680 testing of this unit will verify the 321 00:16:46,160 --> 00:16:41,110 segment's built by North American to be 322 00:16:50,070 --> 00:16:46,170 flown on si 203 and subsequent vehicles 323 00:16:52,290 --> 00:16:50,080 work continued on SIU 201 with 324 00:16:54,230 --> 00:16:52,300 installation of inserts to allow bolting 325 00:16:57,030 --> 00:16:54,240 of all mounting pads to the structure 326 00:16:58,890 --> 00:16:57,040 component installation will be completed 327 00:17:01,200 --> 00:16:58,900 next quarter with checkout also 328 00:17:03,270 --> 00:17:01,210 scheduled for next quarter component 329 00:17:08,010 --> 00:17:03,280 installation is also well underway on 330 00:17:09,929 --> 00:17:08,020 SIU 202 work is well underway at 331 00:17:12,420 --> 00:17:09,939 Marshall system development facility 332 00:17:14,880 --> 00:17:12,430 with installation of black boxes on IU 333 00:17:16,860 --> 00:17:14,890 simulator cold plates and scheduled 334 00:17:18,510 --> 00:17:16,870 vehicle hardware check out the 335 00:17:22,770 --> 00:17:18,520 breadboard is expected to be fully 336 00:17:25,319 --> 00:17:22,780 operational by September meanwhile work 337 00:17:27,110 --> 00:17:25,329 continues toward activation of IBM's I 338 00:17:30,900 --> 00:17:27,120 you check out station at Huntsville 339 00:17:32,790 --> 00:17:30,910 Atmos you ii up to s1 check out stations 340 00:17:35,310 --> 00:17:32,800 to be modified to the s-1 b 341 00:17:40,200 --> 00:17:35,320 configuration was completed in 342 00:17:42,360 --> 00:17:40,210 a summary of the Saturn one 1b program 343 00:17:49,230 --> 00:17:42,370 from April through the end of June shows 344 00:17:58,460 --> 00:17:49,240 major accomplishments in all areas the 345 00:18:07,230 --> 00:18:02,150 preparations for the flight of s 8n 346 00:18:10,880 --> 00:18:07,240 Saturn 1b stage build-up acceleration of 347 00:18:13,320 --> 00:18:10,890 events within the j2 engine program and 348 00:18:16,710 --> 00:18:13,330 continued buildup of ground support 349 00:18:18,960 --> 00:18:16,720 equipment during the next report period 350 00:18:21,180 --> 00:18:18,970 additional major milestones will be 351 00:18:25,100 --> 00:18:21,190 reached strengthening the established